- Page 2 - Page 3 - Page 4 - Page 5 - Page 6 - Page 7 - Page 8 - Page 9 - Page 10 - Page 11 - Page 12 - Page 13 - Page 14 - Page 15 - Page 16 - Page 17 - Page 18 - Page 19 - Page 20 - Page 21 - Page 22 - Page 23 - Page 24 - Page 25 - Page 26 - Page 27 - Page 28 - Page 29 - Page 30 - Page 31 - Page 32 - Page 33 - Page 34 - Page 35 - Page 36 - Page 37 - Page 38 - Page 39 - Page 40 - Page 41 - Page 42 - Page 43 - Page 44 - Page 45 - Page 46 - Page 47 - Page 48 - Page 49 - Page 50 - Page 51 - Page 52 - Page 53 - Page 54 - Page 55 - Page 56 - Page 57 - Page 58 - Page 59 - Page 60 - Page 61 - Page 62 - Page 63 - Page 64 - Flash version © UniFlip.com |
4
PRACTICAL MAXIMUM CAPACITY OF HKIA’S TWO-RUNWAY SYSTEM
• Mixed operation – both arrivals and departures are allowed on each runway. NATS concluded that given HKIA’s special circumstances (for example, terrain constraint surrounding HKIA including the Lantau Peak, Lo Fu Tau and Sunset Peak on Lantau Island as well as Tai Mo Shan and Castle Peak, congested and complicated airspace management, the aircraft mix at HKIA, etc.) and to remain fully in compliance with ICAO’s safety and minimum separation requirements, the practical maximum runway capacity of HKIA can only be increased from 61 to 68 ATMs per hour by 2015 regardless of the mode of operation. This has been verified and accepted by CAD. On the basis of 68 ATMs per hour, NATS assessed that the practical maximum daily movements is about 1,200 per day. This assessment
was based on the historical flight movement pattern of a typical busy day and having taken into account – (a) Alternate closure of the two runways each night for about 8 hours for routine maintenance; (b) The matching of slot availability at HKIA and the destination airports; (c) Typical hourly fluctuations of a busy day; and (d) Provision for recovery periods to cater for operational delays. The practical maximum daily movements of 1,200 can be translated into the practical maximum annual movements of 420,000, taking into account the historical seasonal adjustment of flight movements by airlines as reflected in their flight schedule published twice a year for the summer and winter seasons respectively. The practical maximum annual movement capacity is
expected to be reached sometime between 2019 and 2022 as indicated in Figure 4.2.
LATEST DEVELOPMENTS
To support HKIA’s continued growth, we have committed HK$9.3 billion to the first phase of the Midfield Development which will enable HKIA to optimally accommodate, in terms of both its terminal and apron facilities, approximately 60 million passengers and 5 million tonnes of cargo per year. This is mainly to meet the additional passenger and freighter aircraft stands demand in the interim, while maintaining HKIA’s high service standards. The project involves – (a) The construction of 20 aircraft parking stands including 11 airbridge-served stands, as well as an “I-shaped” passenger concourse at the Midfield;
Figure
4.2
Forecast Air Traffic Movements to Reach the Two-Runway Capacity Between 2019 and 2022
ATMs/Year 700,000 600,000 2019 500,000 Capacity of Two Runways 400,000 300,000 200,000 2008 2009 2010 2011 2012 2013 2014 2015 2016 2017 2018 2019 2020 2021 2022 2023 2024 2025 2026 2027 2022
CAGR 2008-2030 3.6% 3.2% 2.8%
2028
2029
Low
Base
High
24
2030
|