- Page 1
- Page 2 - Page 3 - Page 4 - Page 5 - Page 6 - Page 7 - Page 8 - Page 9 - Page 10 - Page 11 - Page 12 - Page 13 - Page 14 - Page 15 - Page 16 - Page 17 - Page 18 - Page 19 - Page 20 - Page 21 - Page 22 - Page 23 - Page 24 - Page 25 - Page 26 - Page 27 - Page 28 - Page 29 - Page 30 - Page 31 - Page 32 - Page 33 - Page 34 - Page 35 - Page 36 - Page 37 - Page 38 - Page 39 - Page 40 - Page 41 - Page 42 - Page 43 - Page 44 - Page 45 - Page 46 - Page 47 - Page 48 - Page 49 - Page 50 - Page 51 - Page 52 - Page 53 - Page 54 - Page 55 - Page 56 - Page 57 - Page 58 - Page 59 - Page 60 - Page 61 - Page 62 - Page 63 - Page 64 - Flash version © UniFlip.com |
Figure
5.4
14 12 10 8 6 4 2 0 -2 -4
Base Case Constrained Cargo Traffic Forecast
millions of tonnes
millions of tonnes Unconstrained Demand Forecast Constrained Demand Forecast Lost Cargo Throughput
2015 4.4 4.4 0.0
2020 5.6 5.6 0.0
2025 7.2 5.8 -1.4
2030 8.9 6.0 -2.9
5
2007
2008
2009
2010
2011
2012
2013
2014
2015
2016
2017
2018
2019
2020
2021
2022
2023
2024
2025
2026
2027
2028
2029
2030
OPTION 1: TWORUNWAY SYSTEM
Unconstrained Demand Forecast
Constrained Demand Forecast
Lost Cargo Throughput
(e) Road network and landside transportation facilities expansion (HK$3.8 billion) • undertake road network improvement works – approximately 6km of road and 2km of viaduct and ramp improvement works at the South Interchange, Chun Wan Road, Chun Yue Road and Chek Lap Kok South Road • construct two multi-storey car parks comprising a total of 2,800 car parking spaces with coach staging • relocate existing Limousine Lounge
In line with the growth of air traffic, relevant aviation support functions may also need to be expanded, such as the air cargo terminal, freight forwarding and logistics, aircraft maintenance, business aviation centre, inflight catering, ground support equipment maintenance, etc. Under this option, sufficient area on the airport island (about 40 hectares) has been reserved for these purposes. According to the current policies, these facilities are to be provided through franchises and franchisees would be responsible for the capital investment involved. Figure 5.1 highlights the planned developments under Option 1.
Under this option, HKIA will be able to cope with air traffic demand up to 2020 (base case) (see Figure 5.2). Beyond that, HKIA would not be able to accommodate any more additional flight movements. While runway capacity would be reached in 2020 (base case), the actual passengers and cargo throughput would continue to grow nominally beyond 2020, up to HKIA’s maximum handling capacity of 74 million passengers and 6 million tonnes of cargo (see Figures 5.3 and 5.4). This is because of the natural changes in air traffic pattern when the airport reaches its runway capacity (for example, airlines’ tendency to switch to larger aircraft). The implications of reaching runway capacity are discussed in Chapter 7.
HKIA MASTER PLAN 2030
31
|