- Page 2 - Page 3 - Page 4 - Page 5 - Page 6 - Page 7 - Page 8 - Page 9 - Page 10 - Page 11 - Page 12 - Page 13 - Page 14 - Page 15 - Page 16 - Page 17 - Page 18 - Page 19 - Page 20 - Page 21 - Page 22 - Page 23 - Page 24 - Page 25 - Page 26 - Page 27 - Page 28 - Page 29 - Page 30 - Page 31 - Page 32 - Page 33 - Page 34 - Page 35 - Page 36 - Page 37 - Page 38 - Page 39 - Page 40 - Page 41 - Page 42 - Page 43 - Page 44 - Page 45 - Page 46 - Page 47 - Page 48 - Page 49 - Page 50 - Page 51 - Page 52 - Page 53 - Page 54 - Page 55 - Page 56 - Page 57 - Page 58 - Page 59 - Page 60 - Page 61 - Page 62 - Page 63 - Page 64 - Flash version © UniFlip.com |
OPTION 1: TWO-RUNWAY SYSTEM
Under Option 1, we have examined to what extent airport infrastructure and facilities at Hong Kong International Airport (HKIA) could be further enhanced to fully support the practical maximum air traffic movements (ATMs, also known as flight movements) capacity of the two-runway system (420,000 ATMs/ year), without compromising service quality.
CAPITAL INVESTMENT
By continuing the Midfield development and further expanding the following facilities, at an estimated cost of approximately HK$23.4 billion (in 2010 dollars) or HK$42.5 billion (at money-of-the-day [MOD] prices)9, including provisions for design, project management and contingency, phased over 15 years between 2016 and 203010, HKIA’s capacity could be increased to handle a maximum of about 74 million passengers and 6 million tonnes of cargo annually.
9
The final construction cost of the capital projects will be increased from the current estimate based on 2010 dollars to the MOD amounts, in line with the Tender Price Index (TPI) which is estimated to increase at the rate of 5% per annum from 2011 to 2014, 5.5% per annum from 2015 to 2020 and 3% per annum thereafter. The cost breakdown is in 2010 dollars.
10
28
|