- Page 2 - Page 3 - Page 4 - Page 5 - Page 6 - Page 7 - Page 8 - Page 9 - Page 10 - Page 11 - Page 12 - Page 13 - Page 14 - Page 15 - Page 16 - Page 17 - Page 18 - Page 19 - Page 20 - Page 21 - Page 22 - Page 23 - Page 24 - Page 25 - Page 26 - Page 27 - Page 28 - Page 29 - Page 30 - Page 31 - Page 32 - Page 33 - Page 34 - Page 35 - Page 36 - Page 37 - Page 38 - Page 39 - Page 40 - Page 41 - Page 42 - Page 43 - Page 44 - Page 45 - Page 46 - Page 47 - Page 48 - Page 49 - Page 50 - Page 51 - Page 52 - Page 53 - Page 54 - Page 55 - Page 56 - Page 57 - Page 58 - Page 59 - Page 60 - Page 61 - Page 62 - Page 63 - Page 64 - Flash version © UniFlip.com |
Figure
5.1
Option 1 – Airport Layout Plan in 2030
5
OPTION 1: TWORUNWAY SYSTEM
(a) Passenger terminal expansion (HK$6.9 billion) • expand Terminal 1’s gross floor area by 14%, or 82,000 square metres, to provide additional space required for more check-in counters and roadside kerb at departure level, baggage reclaim carousels at arrival level, immigration/customs/ security processing facilities and more room in general for circulation and amenities • increase check-in counters at Terminal 2 from the existing 56 to 112
(b) Apron and passenger concourse expansion (HK$8.3 billion) • expand the Midfield concourse, including the addition of a second I-shaped passenger concourse • add another 20 remote stands for freighters and another 20 airbridge-served passenger aircraft stands at the Midfield (c) Automated People Mover (APM) extension (HK$2.3 billion)
• extend the APM system to reach the new second “I-shaped” passenger concourse at the Midfield (d) Baggage Handling System (BHS) enhancement (HK$2.1 billion) • develop additional baggage make-up laterals and reclaim carousels within the expanded footprint of Terminal 1 • develop a new high-speed baggage system for the Midfield passenger concourses
HKIA MASTER PLAN 2030
29
|